Theses
Supervised:
Past
Current
<< Theses
Intro
<<
Home Page
|
Dissertation
Abstract of Mohamed Ahmed:
Neglecting
uncertainties in the estimation of activities, costs, and durations
can significantly contribute to overruns in a project’s budget
and schedule. On the other hand, properly enforced penalties and incentives
can motivate contractors to finish on time and within the allotted budget.
However, the current literature on this topic does not sufficiently
address project penalties and incentives within the context of uncertainty
and dependence. Thus, this dissertation considers how allocating penalties
and incentives can impact a stochastic project network in which activity
durations are random variables, and some of the activities are subcontracted.
The impact of penalty/incentive schemes on project and activities uncertainties
is also examined. Overall, one of the main pursued benefits of this
work is to provide project stakeholders with a tool that can help determine
the appropriate penalty and incentive rates for outsourced activities
when creating the contract.
The study revealed that a total allocation of a project level penalty/incentive
to relevant activities was considered a fair allocation. A Monte Carlo
Simulation model (MCS) was used to generate random variables, incorporate
activity distributions, incorporate dependence uncertainties, and to
examine the effect the penalty/incentive scheme has on the aggregated
project cost. In order to validate the simulation model, its outcomes
were verified with deterministic outcomes. Furthermore, based on the
several allocation methods explored, the most adequate allocation method
found was the normalized allocation of project penalty/incentive to
activities based on the probability of a zero slack activity lying on
the critical path. The presented MCS model was then expanded and applied
on a larger network. The results of this study demonstrated that the
penalty/incentive scheme can increase the project uncertainty at earlier
stages of the project, but by using the proper allocation method at
later stages, it is contained to the baseline levels that do not comprise
any penalty/incentive. The study also revealed that the common practice
of assuming project activities as being independent underestimates the
most critical, not the least critical, activities’ penalty/incentive
rates.
<<
Back
|